Final Concrete Pour 31st Jan

Update from Park Developments;

We will be carrying out our final basement slab concrete pour on Wednesday 31st January, subject to favourable weather conditions.

The location of the works is at apartment Block 1, Glencairn, situated at the northern end of the Project site adjacent to the tower crane. As before, we plan to start delivery of concrete from 07.00am. The concrete will be
pumped into position and this operation will conclude in late afternoon.